Net Billing Pakistan 2026 — NEPRA Rules, Rates & Payback

⚡ Net Billing in Pakistan 2026 — NEPRA's New Rules, Rates & What They Mean for Your Solar Payback

On 9 February 2026, NEPRA rewrote the economics of rooftop solar in Pakistan: the old net metering system — every exported unit cancelling an imported one — is gone for new applicants, replaced by net billing. Exports now earn roughly Rs. 10 per unit while imports still cost Rs. 40–60. This guide explains what changed, who keeps the old deal, and how to size a system that still pays back fast.

📅 Updated November 2026  |  🇵🇦 Pakistan  |  ⏱️ 8 min read

📋 SRO 251(I)/2026 💰 Buyback ~Rs. 10/unit 📅 5-Year Agreements 🏠 Self-Consumption First
📊 See the Worked Bill Example
Rs. 8–11 New export buyback / unit
Rs. 25–27 Old buyback / unit (grandfathered)
5 yrs New agreement term
~85% Self-consumption with a battery

1. What Changed on 9 February 2026

On 9 February 2026, NEPRA notified the Prosumer Regulations 2026 as SRO 251(I)/2026, repealing the 2015 net-metering regulations. Every new prosumer connection since is governed by net billing — and the difference is worth real money on every bill.

Old system: exported units cancelled imported units one for one — export 400, import 500, pay for 100. That swap is gone. Exports are now bought at the National Average Energy Purchase Price (NAEPP) — about Rs. 8–11 per unit, Rs. 8.13 for April–June 2026, revised quarterly — while imports are billed at your normal retail tariff, Rs. 40–60 at the upper slabs.

NEPRA's argument was that the 1:1 swap let solar households avoid the transmission, distribution and capacity costs built into the retail tariff. The practical result: exported solar is worth roughly a fifth of what it was, and a system's value has shifted from selling power to using it yourself.

⚠️ The old deal still exists for some people. Agreements signed — or applications filed — before 9 February 2026 keep the old buyback rate until expiry. See section 4 before you change anything about your system.

2. Net Metering vs Net Billing — Old vs New

The buyback rate gets the headlines, but the contract length, the installer-certification change and the new transformer cap all matter when you plan a system.

RuleOld net metering (before 9 Feb 2026)New net billing (from 9 Feb 2026)
Export buyback~Rs. 25.32–27 per unit (1:1 retail offset)NAEPP, about Rs. 8–11 per unit (Rs. 8.13 for Apr–Jun 2026)
Import billingOffset 1:1 against exportsFull retail tariff, Rs. 40–60 per unit at upper slabs
Agreement term7 years5 years, renewable for another 5
System size cap1 MW max, not above sanctioned loadSame cap, plus 80% transformer-capacity limit
Installer certificationAEDB-registered installerPPIB-certified installer
NEPRA concurrenceRequiredNone up to 25 kW; Rs. 1,000/kW fee above 25 kW
On-grid paybackRoughly 2–3 yearsRoughly 3–5 years

3. Worked Bill Example — The Same Household, Two Bills

Take a household importing 500 units and exporting 400 in a month. Same house, same system — only the rules change.

Bill itemOld net meteringNew net billing
Units imported500 units500 units
Units exported400 units400 units
Import charge—500 × Rs. 50 = Rs. 25,000
Export credit400 units offset 400 imports400 × Rs. 10 = Rs. 4,000
Net energy bill100 net units × Rs. 50 = Rs. 5,000Rs. 25,000 − Rs. 4,000 = Rs. 21,000

The gap is the whole story: those 400 exported units were worth Rs. 20,000 under the old swap and Rs. 4,000 now. Every unit you use yourself is worth Rs. 50; every unit you export is worth Rs. 10 — so the household that runs its washing machine and air conditioner while the sun shines saves five times more per unit than one that exports the same power and buys it back at night.

4. Who Is Grandfathered — and Who Isn't

If your net metering agreement was signed — or your application filed — before 9 February 2026, you keep the old buyback rate until your contract expires. An April 2026 amendment, retrospective to 9 February, confirmed this protection.

One catch: a material modification forfeits the protection — expanding your array moves the whole system onto net billing, so a grandfathered household adding panels for a new air conditioner can end up worse off.

If you are grandfathered, check with your DISCO in writing before touching your system. If you are buying now, you are a net-billing customer from day one, and the next section's sizing logic applies to you.

5. What It Means for Your Payback

Under net billing, monthly saving = self-used units × tariff + exported units × buyback rate. The tariff side is five times bigger — which is why self-consumption decides whether a system pays back in three years or five.

Suppose your system generates 500 units a month: 300 used directly, 200 exported. Saving: 300 × Rs. 50 + 200 × Rs. 10 = Rs. 17,000 — against Rs. 25,000 under the old 1:1 rules. The system has not changed; the arithmetic has.

On-grid payback has lengthened from roughly 2–3 years to roughly 3–5 years — still strong, but no longer the near-instant payback the old figures suggested. Three things protect it:

  • Shift daytime loads into solar hours. Run the water pump, washing machine and air conditioner while your panels are producing, instead of exporting at Rs. 10 and buying back at Rs. 50.
  • Size for daytime consumption, not your total bill. A system covering what you use between sunrise and sunset wastes far less on low-value exports than an oversized one.
  • Add a battery. Storage pushes self-consumption to around 85% — midday power is still yours at night — and a hybrid system keeps paying during load-shedding, where generator savings are unchanged by net billing.

6. How to Apply Under the New Rules

The process itself is largely unchanged — what changed is who certifies your installer and who approves your system:

  • Choose a PPIB-certified installer — certification moved from AEDB to PPIB in 2026, so an old AEDB certificate no longer proves anything.
  • Apply through the PITC portal or your DISCO. Applications go through nmp.pitc.com.pk or your DISCO's Customer Service Centre; LESCO and K-Electric also run their own online portals.
  • Systems up to 25 kW are approved by your DISCO alone — no NEPRA concurrence needed since 6 August 2026 (SRO 1330(I)/2026). Above 25 kW, concurrence still applies at Rs. 1,000 per kW (SRO 709(I)/2026).
  • Check transformer headroom early. Your DISCO can refuse an application if solar on your local transformer has reached 80% of capacity — a real risk where every other roof already has panels.
  • Stay within your sanctioned load. No system can exceed the sanctioned load on your bill or 1 MW — apply to raise your sanctioned load first if you need more.

Once approved, your agreement runs five years, renewable for five more — shorter than the old seven-year term.

7. Net Billing by DISCO

The rules are national, set by NEPRA — but applications go through your DISCO, and timelines differ. Each guide below carries its own net-billing section.

⚡

LESCO — Lahore

4–8 weeks

Shortest approval timeline of any DISCO, with its own net-billing portal.

⚡

IESCO — Islamabad

5–10 weeks

Islamabad and Rawalpindi; the strictest technical inspection of any DISCO.

⚡

FESCO — Faisalabad

6–12 weeks

Faisalabad division; apply at the FESCO Customer Service Centres.

⚡

GEPCO — Gujranwala

7–13 weeks

Gujranwala division; allow extra time for inspection in outstation areas.

⚡

HESCO — Hyderabad

8–16 weeks

Hyderabad and interior Sindh; long timelines — apply early.

⚡

MEPCO — Multan

6–12 weeks

Multan and south Punjab; daytime-load sizing pays off especially well here.

⚡

PESCO — Peshawar

8–16 weeks

Peshawar and Khyber Pakhtunkhwa; complete paperwork first time matters most.

⚡

SEPCO — Sukkur

10–18 weeks

Sukkur and upper Sindh; the longest timeline in the country — start early.

⚡

K-Electric — Karachi

6–14 weeks, portal-based

Karachi's private utility; applications run through its own online portal.

8. Frequently Asked Questions

Not for new applicants: since 9 February 2026, every new connection is on net billing under NEPRA's Prosumer Regulations 2026 (SRO 251(I)/2026). Old terms survive only for agreements signed — or applications filed — before that date, until expiry.

Exports are bought at the National Average Energy Purchase Price (NAEPP), about Rs. 8–11 per unit — Rs. 8.13 for April–June 2026. NEPRA revises it quarterly, so confirm the current rate with your DISCO first.

No — an April 2026 amendment, retrospective to 9 February, confirmed pre-existing agreements keep the old rate until expiry. Only a material modification, such as expanding your system, ends that protection.

Yes — but the maths has changed. A unit you use yourself is worth your full retail tariff (Rs. 40–60); a unit you export earns about Rs. 10. Size for daytime consumption and, budget allowing, add a battery to lift self-consumption to around 85%. On-grid payback is now roughly 3–5 years.

Up to 25 kW, no — since 6 August 2026 (SRO 1330(I)/2026) your DISCO approves the connection alone. Above 25 kW, NEPRA concurrence still applies at Rs. 1,000 per kW (SRO 709(I)/2026). Either way, your installer must be PPIB-certified.