GEPCO Net Metering 2026 — Complete Process, Fees, Documents & Timeline

🔌 GEPCO Net Metering 2026 — Complete Process, Fees, Documents & Timeline

Everything you need to know about GEPCO net metering in Gujranwala / Sialkot: step-by-step application, complete documents checklist, exact fees in PKR, inspection timeline, billing explained, savings calculator and what to do if GEPCO delays your application.

📅 Updated May 2026  |  ⚡ GEPCO — Gujranwala  |  ⏱️ 7 min read

📋 Step-by-Step Process 📄 Documents Checklist 💰 Fees in PKR ⏱️ 7–13 weeks Timeline

1. GEPCO — Gujranwala Electric Power Company Overview

GEPCO (Gujranwala Electric Power Company) supplies electricity to Gujranwala, Sialkot, Narowal, Hafizabad, Mandi Bahauddin, Gujrat. Net metering under NEPRA's regulations is available across all GEPCO territory for residential, commercial and industrial consumers.

7–13 weeks
Approval timeline
5.0hr
Peak sun hours/day
25 yrs
Net metering license
Moderate
vs other DISCOs

GEPCO area-specific solar context:

  • GEPCO area includes Punjab's export industry hub — Sialkot's surgical and sports goods industry has driven large commercial solar adoption
  • Gujranwala has very strong industrial solar market — good local installer expertise and component availability
  • Sialkot areas typically have better grid quality than Gujranwala industrial areas
  • GEPCO processing is moderate — G.T. Road CSC (Gujranwala) is the main net metering office
  • Rural outstation areas (Narowal, Hafizabad) may have limited AEDB-registered installer access — verify before committing

2. Who is Eligible for GEPCO Net Metering?

  • GEPCO connection: Your electricity must be supplied by GEPCO — covers Gujranwala, Sialkot, Narowal, Hafizabad, Mandi Bahauddin, Gujrat
  • System size: Solar system capacity must not exceed your sanctioned load. Check your bill for sanctioned load in kW.
  • Consumer categories: Domestic (residential), commercial and industrial connections are all eligible
  • NEPRA-approved inverter: Must use an inverter on NEPRA's approved equipment list — all major brands are included (verify your exact model)
  • AEDB-registered installer: System must be installed by an AEDB-registered installer — required for application submission
  • Maximum system: Up to 1,000kW (1MW) — residential systems are well within this limit
⚠️ Sanctioned load check: If you want to install a system larger than your sanctioned load, apply to GEPCO to increase your sanctioned load first (separate application and fee). Check your electricity bill — it shows sanctioned load in kW.

3. GEPCO Net Metering Application — Step by Step

1

Choose AEDB-Registered Installer

Only AEDB-registered installers can submit GEPCO net metering applications. Verify AEDB certificate before signing any contract. Ask for their GEPCO net metering track record — prior approved applications in your area indicate familiarity with GEPCO's specific requirements.

Before everything
2

Solar System Installation

Complete solar installation per NEPRA technical standards. Inverter must be on GEPCO's approved list. All wiring, earthing, protection devices (SPD, MCB) must meet standards. Photograph the completed installation — GEPCO inspectors may compare against single-line diagram.

Before application
3

Prepare & Submit Application

Your installer compiles all technical documents and submits with your personal documents at the GEPCO Customer Service Centre covering your area. Pay the application processing fee. Get the reference number and submission date in writing — keep this safe for follow-up.

Day 1 — 7–13 weeks clock starts
4

GEPCO Technical Inspection

GEPCO's inspection team visits your premises. Be present with your installer. They check: inverter model vs approved list, DC/AC wiring, earthing, surge protection device (SPD), disconnection switches, and overall installation quality. Ensure everything matches your submitted single-line diagram.

3–6 weeks after submission
5

Approval & Meter Installation

After passing inspection, GEPCO issues approval and schedules bi-directional meter installation. The new meter records both imported and exported units. Net metering credits begin from the next billing cycle. Your 25-year net metering license is issued.

2–4 weeks after inspection
Total GEPCO timeline: 7–13 weeks from complete application submission. If inspection fails (most common: missing SPD, incorrect earthing, inverter mismatch), rectify and request re-inspection — adds 2–4 weeks. Ensure everything is perfect before inspection to avoid restart delays.

4. Required Documents — Complete Checklist

📋 You Provide

  • CNIC copy (electricity account holder)
  • Latest GEPCO electricity bill
  • Completed application form (GEPCO CSC se milega)
  • Property ownership proof or tenancy agreement
  • Passport-size photograph (account holder)

🔧 Installer Prepares

  • Single-line electrical diagram
  • Inverter datasheet + NEPRA approval certificate
  • Solar panel technical datasheets
  • AEDB installer registration certificate
  • Installation completion certificate (signed)
  • System summary (capacity, panel count, inverter model)

Make 3 complete sets of all documents. Keep submission receipt with date stamp. Photograph every document before submission. Incomplete applications are the primary cause of delays — get everything right first time.

5. GEPCO Net Metering Fees in PKR 2026

Fee ItemAmount (PKR)Paid ToWhen
Application Processing FeeRs. 3,000–5,000GEPCO (at CSC)Application submission
Bi-Directional MeterRs. 3,500–7,000GEPCOMeter installation
Meter Sealing FeeRs. 1,000–2,000GEPCOMeter installation
Installer Handling FeeRs. 10,000–20,000Your installerIn installation contract
Total Government FeesRs. 7,500–14,000GEPCO directlySplit across process

Confirm the installer's net metering handling fee is explicitly included in your written installation contract before signing. Some budget installers exclude this and charge separately later.

6. GEPCO Customer Service Centre Locations

  • Gujranwala Main CSC: G.T. Road, Gujranwala — Primary net metering office
  • Sialkot CSC: Paris Road, Sialkot
  • Gujrat CSC: Local GEPCO office, Gujrat
  • Hafizabad / Narowal CSC: Local offices — outstation areas

Always submit at the CSC covering your connection's division. Check your GEPCO electricity bill header for your division code. Submitting to the wrong CSC causes redirection delays of 1–2 weeks.

⚠️ Helpline: GEPCO helpline 055-111-000-118 — reference your application number for status updates. Follow up every 2 weeks if no response. For escalation beyond GEPCO: NEPRA consumer complaint portal at nepra.org.pk — NEPRA mandates 30-day processing from complete application.

7. GEPCO Net Metering Billing Explained

After bi-directional meter installation, your monthly bill changes significantly:

Bill ItemMeaningExample (5kW system)
Units ImportedElectricity drawn from GEPCO grid~270 units/month
Units ExportedExcess solar exported to grid~260 units/month
Net UnitsImport minus export (what you pay for)~10 net units
Energy ChargesNet units × tariff rate~Rs. 450
Fixed ChargesMeter rent + surcharges (NOT offset by solar)Rs. 1,500–3,500
Total BillEnergy + fixed + taxes~Rs. 3,000–6,000
Pre-solar billWithout solar (same consumption)~Rs. 24,000+
⚠️ Fixed charges (meter rent, Fuel Adjustment Charges, taxes) are NOT offset by solar generation. Your GEPCO bill will never go to zero — minimum Rs. 1,500–3,500/month even with large solar system. This is normal for all DISCOs.

GEPCO follows NEPRA net metering regulations. Export rate is at avoided cost — lower than retail tariff. Confirm current rate with GEPCO billing. Net metering credit roll-forward applies month-to-month with annual settlement.

8. How Much You Save with GEPCO Net Metering

GEPCO area has 5.0 peak sun hours/day — good solar resource.

System SizeMonthly GenerationMonthly Bill ReductionAnnual SavingsPayback (On-Grid)
3 kW~318 kWhRs. 14,340–15,535~Rs. 172,200~2 yrs
5 kW~531 kWh/month~Rs. 23,900/month~Rs. 2.87 Lac/year~2 yrs
7 kW~743 kWhRs. 33,460–35,850~Rs. 401,800~2 yrs
10 kW~1062 kWhRs. 47,800–50,190~Rs. 574,000~1.9 yrs

After 15% system losses. Savings at Rs. 45/unit. Load-shedding areas: add Rs. 10,000–20,000/month hybrid generator savings.

Load-shedding bonus: For GEPCO areas with 8–12 hrs daily load-shedding — a hybrid system with 10kWh Pylontech battery adds Rs. 10,000–20,000/month in eliminated generator costs, improving payback period to 2.5–3.5 years even on higher-cost hybrid systems.

9. GEPCO-Specific Notes & Tips

GEPCO's Sialkot division has strong solar adoption due to industrial export sector demands for uninterrupted power. Residential buyers in Sialkot often benefit from competitive pricing due to the strong installer market. Gujranwala residential areas have significant load-shedding — hybrid systems strongly recommended.

Load-shedding by area:

Gujranwala city: 8–12 hrs. Sialkot: 6–10 hrs. Narowal/Hafizabad: 10–14 hrs. Rural: 12–16 hrs.

Best inverter recommendation for GEPCO area:

For most GEPCO residential buyers: GoodWe ES/EM hybrid inverter is the top recommendation — sub-20ms switching handles Pakistan's sudden load-shedding, generator input is critical for GEPCO's outage hours, and SEMS monitoring lets you track generation from your phone. Solis RHI is the best budget alternative. Avoid on-grid inverters in any GEPCO area with 6+ hours daily load-shedding.

Frequently Asked Questions

GEPCO net metering typically takes 7–13 weeks: Gujranwala city 7–10 weeks. Sialkot 7–11 weeks. Outstation areas (Narowal, Hafizabad, Mandi Bahauddin) 10–15 weeks. Submit at Gujranwala G.T. Road CSC for fastest processing. Ensure all documents are complete — GEPCO is strict about AEDB installer certification.

Yes — strongly. Gujranwala has 5.0 peak sun hours, 8–14 hours daily load-shedding in most areas, and high electricity consumption from industrial activity and household use. A 5kW hybrid system saves Rs. 35,000–45,000/month including generator elimination. Payback 2.5–3.5 years.

Yes — Sialkot is in GEPCO territory. Apply at the Sialkot CSC (Paris Road). Same process and fees as Gujranwala. Sialkot's strong industrial installer market means good local AEDB installer availability. Sialkot residential areas typically have 6–10 hours load-shedding — hybrid inverter is recommended.

Government fees payable to GEPCO: Application Rs. 3,000–5,000 + Bi-directional meter Rs. 3,500–7,000 + meter sealing Rs. 1,000–2,000 = total Rs. 7,500–14,000. Your installer's handling fee Rs. 10,000–20,000 (confirm this is in your installation contract). Total process cost: Rs. 17,500–34,000 for net metering application.

For Gujranwala/Sialkot hybrid: GoodWe ES/EM is the top pick — widely available locally, sub-20ms switching, generator input (critical for 8–14 hour outages). Solis RHI is the best budget hybrid with generator input. Avoid on-grid inverters in any GEPCO area with 6+ hours load-shedding.

Agricultural connections in GEPCO territory may be eligible for net metering — however, agricultural solar programs often have separate incentives and application processes. Contact GEPCO's agricultural division and also check AEDB's agricultural solar program for subsidized financing options. Agricultural tube well solar typically uses on-grid or off-grid systems without net metering.