MEPCO Net Metering 2026 — Complete Process, Fees, Documents & Timeline

🔌 MEPCO Net Metering 2026 — Complete Process, Fees, Documents & Timeline

Everything you need to know about MEPCO net metering in Multan / South Punjab: step-by-step application, complete documents checklist, exact fees in PKR, inspection timeline, billing explained, savings calculator and what to do if MEPCO delays your application.

📅 Updated May 2026  |  ⚡ MEPCO — Multan  |  ⏱️ 7 min read

📋 Step-by-Step Process 📄 Documents Checklist 💰 Fees in PKR ⏱️ 6–12 weeks Timeline

1. MEPCO — Multan Electric Power Company Overview

MEPCO (Multan Electric Power Company) supplies electricity to Multan, Bahawalpur, DG Khan, Rahim Yar Khan, Lodhran, Vehari, Khanewal, Sahiwal. Net metering under NEPRA's regulations is available across all MEPCO territory for residential, commercial and industrial consumers.

6–12 weeks
Approval timeline
5.5hr
Peak sun hours/day
25 yrs
Net metering license
Moderate
vs other DISCOs

MEPCO area-specific solar context:

  • MEPCO covers Pakistan's hottest districts — DG Khan summer temperatures exceed 50°C
  • 5.5 peak sun hours/day — 10% better generation than Lahore
  • High load-shedding (8–18 hrs) makes hybrid systems essential across all MEPCO area
  • N-Type TOPCon panels worth premium for DG Khan/Rajanpur extreme heat zones
  • Moderate processing speed — Multan Abdali Road CSC is fastest

2. Who is Eligible for MEPCO Net Metering?

  • MEPCO connection: Your electricity must be supplied by MEPCO — covers Multan, Bahawalpur, DG Khan, Rahim Yar Khan, Lodhran, Vehari, Khanewal, Sahiwal
  • System size: Solar system capacity must not exceed your sanctioned load. Check your bill for sanctioned load in kW.
  • Consumer categories: Domestic (residential), commercial and industrial connections are all eligible
  • NEPRA-approved inverter: Must use an inverter on NEPRA's approved equipment list — all major brands are included (verify your exact model)
  • AEDB-registered installer: System must be installed by an AEDB-registered installer — required for application submission
  • Maximum system: Up to 1,000kW (1MW) — residential systems are well within this limit
⚠️ Sanctioned load check: If you want to install a system larger than your sanctioned load, apply to MEPCO to increase your sanctioned load first (separate application and fee). Check your electricity bill — it shows sanctioned load in kW.

3. MEPCO Net Metering Application — Step by Step

1

Choose AEDB-Registered Installer

Only AEDB-registered installers can submit MEPCO net metering applications. Verify AEDB certificate before signing any contract. Ask for their MEPCO net metering track record — prior approved applications in your area indicate familiarity with MEPCO's specific requirements.

Before everything
2

Solar System Installation

Complete solar installation per NEPRA technical standards. Inverter must be on MEPCO's approved list. All wiring, earthing, protection devices (SPD, MCB) must meet standards. Photograph the completed installation — MEPCO inspectors may compare against single-line diagram.

Before application
3

Prepare & Submit Application

Your installer compiles all technical documents and submits with your personal documents at the MEPCO Customer Service Centre covering your area. Pay the application processing fee. Get the reference number and submission date in writing — keep this safe for follow-up.

Day 1 — 6–12 weeks clock starts
4

MEPCO Technical Inspection

MEPCO's inspection team visits your premises. Be present with your installer. They check: inverter model vs approved list, DC/AC wiring, earthing, surge protection device (SPD), disconnection switches, and overall installation quality. Ensure everything matches your submitted single-line diagram.

3–6 weeks after submission
5

Approval & Meter Installation

After passing inspection, MEPCO issues approval and schedules bi-directional meter installation. The new meter records both imported and exported units. Net metering credits begin from the next billing cycle. Your 25-year net metering license is issued.

2–4 weeks after inspection
Total MEPCO timeline: 6–12 weeks from complete application submission. If inspection fails (most common: missing SPD, incorrect earthing, inverter mismatch), rectify and request re-inspection — adds 2–4 weeks. Ensure everything is perfect before inspection to avoid restart delays.

4. Required Documents — Complete Checklist

📋 You Provide

  • CNIC copy (electricity account holder)
  • Latest MEPCO electricity bill
  • Completed application form (MEPCO CSC se milega)
  • Property ownership proof or tenancy agreement
  • Passport-size photograph (account holder)

🔧 Installer Prepares

  • Single-line electrical diagram
  • Inverter datasheet + NEPRA approval certificate
  • Solar panel technical datasheets
  • AEDB installer registration certificate
  • Installation completion certificate (signed)
  • System summary (capacity, panel count, inverter model)

Make 3 complete sets of all documents. Keep submission receipt with date stamp. Photograph every document before submission. Incomplete applications are the primary cause of delays — get everything right first time.

5. MEPCO Net Metering Fees in PKR 2026

Fee ItemAmount (PKR)Paid ToWhen
Application Processing FeeRs. 3,000–5,000MEPCO (at CSC)Application submission
Bi-Directional MeterRs. 3,500–7,000MEPCOMeter installation
Meter Sealing FeeRs. 1,000–2,000MEPCOMeter installation
Installer Handling FeeRs. 10,000–20,000Your installerIn installation contract
Total Government FeesRs. 7,500–14,000MEPCO directlySplit across process

Confirm the installer's net metering handling fee is explicitly included in your written installation contract before signing. Some budget installers exclude this and charge separately later.

6. MEPCO Customer Service Centre Locations

  • Multan Main CSC: Abdali Road, Multan
  • Bahawalpur CSC: Civil Lines, Bahawalpur
  • DG Khan CSC: Local MEPCO office
  • RYK CSC: Local MEPCO office, RYK

Always submit at the CSC covering your connection's division. Check your MEPCO electricity bill header for your division code. Submitting to the wrong CSC causes redirection delays of 1–2 weeks.

⚠️ Helpline: MEPCO helpline 061-111-000-118 — reference your application number for status updates. Follow up every 2 weeks if no response. For escalation beyond MEPCO: NEPRA consumer complaint portal at nepra.org.pk — NEPRA mandates 30-day processing from complete application.

7. MEPCO Net Metering Billing Explained

After bi-directional meter installation, your monthly bill changes significantly:

Bill ItemMeaningExample (5kW system)
Units ImportedElectricity drawn from MEPCO grid~270 units/month
Units ExportedExcess solar exported to grid~260 units/month
Net UnitsImport minus export (what you pay for)~10 net units
Energy ChargesNet units × tariff rate~Rs. 450
Fixed ChargesMeter rent + surcharges (NOT offset by solar)Rs. 1,500–3,500
Total BillEnergy + fixed + taxes~Rs. 3,000–6,000
Pre-solar billWithout solar (same consumption)~Rs. 24,000+
⚠️ Fixed charges (meter rent, Fuel Adjustment Charges, taxes) are NOT offset by solar generation. Your MEPCO bill will never go to zero — minimum Rs. 1,500–3,500/month even with large solar system. This is normal for all DISCOs.

MEPCO export rates follow NEPRA avoided cost framework. High industrial tariffs (Rs. 55–80/unit) make commercial net metering especially attractive. Confirm current export rate with MEPCO billing department.

8. How Much You Save with MEPCO Net Metering

MEPCO area has 5.5 peak sun hours/day — good solar resource.

System SizeMonthly GenerationMonthly Bill ReductionAnnual SavingsPayback (On-Grid)
3 kW~351 kWhRs. 15,795–17,111~Rs. 189,600~2 yrs
5 kW~585 kWh/month~Rs. 26,325/month~Rs. 3.16 Lac/year~2 yrs
7 kW~819 kWhRs. 36,855–39,487~Rs. 442,399~2 yrs
10 kW~1170 kWhRs. 52,650–55,282~Rs. 632,000~1.9 yrs

After 15% system losses. Savings at Rs. 45/unit. Load-shedding areas: add Rs. 10,000–20,000/month hybrid generator savings.

Load-shedding bonus: For MEPCO areas with 8–12 hrs daily load-shedding — a hybrid system with 10kWh Pylontech battery adds Rs. 10,000–20,000/month in eliminated generator costs, improving payback period to 2.5–3.5 years even on higher-cost hybrid systems.

9. MEPCO-Specific Notes & Tips

MEPCO covers Pakistan's extreme heat zones. GoodWe ES hybrid (sub-20ms, generator input) is strongly recommended for MEPCO's 10–18 hour daily load-shedding. For DG Khan and Rajanpur extreme heat (48–52°C): LONGi Hi-MO 9 N-Type panels provide measurably better performance — the premium is justified here.

Load-shedding by area:

Multan city: 8–12 hrs. Bahawalpur: 8–12 hrs. DG Khan/Rajanpur: 10–16 hrs. Rural MEPCO: 14–18 hrs.

Best inverter recommendation for MEPCO area:

For most MEPCO residential buyers: GoodWe ES/EM hybrid inverter is the top recommendation — sub-20ms switching handles Pakistan's sudden load-shedding, generator input is critical for MEPCO's outage hours, and SEMS monitoring lets you track generation from your phone. Solis RHI is the best budget alternative. Avoid on-grid inverters in any MEPCO area with 6+ hours daily load-shedding.

Frequently Asked Questions

6–12 weeks. Multan: 6–9 weeks. Bahawalpur: 7–11 weeks. DG Khan/RYK: 10–14 weeks. Remote rural: 12–16 weeks. Submit at Multan Abdali Road CSC. Escalate to nepra.org.pk if delayed beyond 8 weeks from complete submission.

Strongly yes. 5.5 sun hours + 8–18 hour shedding + high bills = exceptional ROI. 5kW hybrid in Multan saves Rs. 38,000–50,000/month. Payback 2–3 years.

For DG Khan/Rajanpur (48–52°C): N-Type TOPCon strongly recommended — LONGi Hi-MO 9 or JA Solar DeepBlue N-Type. At 80°C roof temperature, N-Type produces 5–8% more than P-Type. Worth the premium in extreme heat. For Multan/Bahawalpur: JA Solar P-Type remains best value.

CNIC copy, latest MEPCO bill, application form, single-line diagram, inverter NEPRA certificate, panel datasheets, AEDB installer certificate, installation completion certificate. Tin complete sets banao. Submission receipt zaroor lo.

GoodWe ES/EM hybrid: sub-20ms + generator input — perfect for MEPCO's extreme load-shedding. For remote rural areas needing off-grid: Solis RHI. Avoid on-grid inverters across virtually all MEPCO territory.

Yes — all MEPCO territory is eligible. Outstation offices: 12–16 weeks. Limited AEDB installer access in remote areas. For 16–18 hour shedding: off-grid system often more practical than waiting for MEPCO net metering.