FESCO Net Metering 2026 — Complete Process, Fees, Documents & Timeline

🔌 FESCO Net Metering 2026 — Complete Process, Fees, Documents & Timeline

Everything you need to know about FESCO net metering in Faisalabad / Sargodha: step-by-step application, complete documents checklist, exact fees in PKR, inspection timeline, billing explained, savings calculator and what to do if FESCO delays your application.

📅 Updated May 2026  |  ⚡ FESCO — Faisalabad  |  ⏱️ 7 min read

📋 Step-by-Step Process 📄 Documents Checklist 💰 Fees in PKR ⏱️ 6–12 weeks Timeline

1. FESCO — Faisalabad Electric Supply Company Overview

FESCO (Faisalabad Electric Supply Company) supplies electricity to Faisalabad, Sargodha, Jhang, Toba Tek Singh, Chiniot, Mianwali. Net metering under NEPRA's regulations is available across all FESCO territory for residential, commercial and industrial consumers.

6–12 weeks
Approval timeline
5.0hr
Peak sun hours/day
25 yrs
Net metering license
Moderate
vs other DISCOs

FESCO area-specific solar context:

  • FESCO area covers Pakistan's industrial heartland — high electricity consumption and significant load-shedding make solar very attractive
  • Faisalabad's 5.0 sun hours/day = same as Lahore — excellent solar resource
  • Industrial areas (Estate, Millat Road) have different feeder schedules — verify actual load-shedding hours with neighbours
  • FESCO processing times are moderate — Canal Road CSC is faster than outstation offices
  • Faisalabad's textile industry has adopted large-scale solar — local installer expertise is strong

2. Who is Eligible for FESCO Net Metering?

  • FESCO connection: Your electricity must be supplied by FESCO — covers Faisalabad, Sargodha, Jhang, Toba Tek Singh, Chiniot, Mianwali
  • System size: Solar system capacity must not exceed your sanctioned load. Check your bill for sanctioned load in kW.
  • Consumer categories: Domestic (residential), commercial and industrial connections are all eligible
  • NEPRA-approved inverter: Must use an inverter on NEPRA's approved equipment list — all major brands are included (verify your exact model)
  • AEDB-registered installer: System must be installed by an AEDB-registered installer — required for application submission
  • Maximum system: Up to 1,000kW (1MW) — residential systems are well within this limit
⚠️ Sanctioned load check: If you want to install a system larger than your sanctioned load, apply to FESCO to increase your sanctioned load first (separate application and fee). Check your electricity bill — it shows sanctioned load in kW.

3. FESCO Net Metering Application — Step by Step

1

Choose AEDB-Registered Installer

Only AEDB-registered installers can submit FESCO net metering applications. Verify AEDB certificate before signing any contract. Ask for their FESCO net metering track record — prior approved applications in your area indicate familiarity with FESCO's specific requirements.

Before everything
2

Solar System Installation

Complete solar installation per NEPRA technical standards. Inverter must be on FESCO's approved list. All wiring, earthing, protection devices (SPD, MCB) must meet standards. Photograph the completed installation — FESCO inspectors may compare against single-line diagram.

Before application
3

Prepare & Submit Application

Your installer compiles all technical documents and submits with your personal documents at the FESCO Customer Service Centre covering your area. Pay the application processing fee. Get the reference number and submission date in writing — keep this safe for follow-up.

Day 1 — 6–12 weeks clock starts
4

FESCO Technical Inspection

FESCO's inspection team visits your premises. Be present with your installer. They check: inverter model vs approved list, DC/AC wiring, earthing, surge protection device (SPD), disconnection switches, and overall installation quality. Ensure everything matches your submitted single-line diagram.

3–6 weeks after submission
5

Approval & Meter Installation

After passing inspection, FESCO issues approval and schedules bi-directional meter installation. The new meter records both imported and exported units. Net metering credits begin from the next billing cycle. Your 25-year net metering license is issued.

2–4 weeks after inspection
Total FESCO timeline: 6–12 weeks from complete application submission. If inspection fails (most common: missing SPD, incorrect earthing, inverter mismatch), rectify and request re-inspection — adds 2–4 weeks. Ensure everything is perfect before inspection to avoid restart delays.

4. Required Documents — Complete Checklist

📋 You Provide

  • CNIC copy (electricity account holder)
  • Latest FESCO electricity bill
  • Completed application form (FESCO CSC se milega)
  • Property ownership proof or tenancy agreement
  • Passport-size photograph (account holder)

🔧 Installer Prepares

  • Single-line electrical diagram
  • Inverter datasheet + NEPRA approval certificate
  • Solar panel technical datasheets
  • AEDB installer registration certificate
  • Installation completion certificate (signed)
  • System summary (capacity, panel count, inverter model)

Make 3 complete sets of all documents. Keep submission receipt with date stamp. Photograph every document before submission. Incomplete applications are the primary cause of delays — get everything right first time.

5. FESCO Net Metering Fees in PKR 2026

Fee ItemAmount (PKR)Paid ToWhen
Application Processing FeeRs. 3,000–5,000FESCO (at CSC)Application submission
Bi-Directional MeterRs. 3,500–7,000FESCOMeter installation
Meter Sealing FeeRs. 1,000–2,000FESCOMeter installation
Installer Handling FeeRs. 10,000–20,000Your installerIn installation contract
Total Government FeesRs. 7,500–14,000FESCO directlySplit across process

Confirm the installer's net metering handling fee is explicitly included in your written installation contract before signing. Some budget installers exclude this and charge separately later.

6. FESCO Customer Service Centre Locations

  • Faisalabad Main CSC: Canal Road, Faisalabad — Primary net metering office
  • Sargodha CSC: University Road, Sargodha
  • Jhang CSC: Civil Lines, Jhang
  • Mianwali CSC: Local FESCO office, Mianwali

Always submit at the CSC covering your connection's division. Check your FESCO electricity bill header for your division code. Submitting to the wrong CSC causes redirection delays of 1–2 weeks.

⚠️ Helpline: FESCO helpline 041-111-000-118 — reference your application number for status updates. Follow up every 2 weeks if no response. For escalation beyond FESCO: NEPRA consumer complaint portal at nepra.org.pk — NEPRA mandates 30-day processing from complete application.

7. FESCO Net Metering Billing Explained

After bi-directional meter installation, your monthly bill changes significantly:

Bill ItemMeaningExample (5kW system)
Units ImportedElectricity drawn from FESCO grid~270 units/month
Units ExportedExcess solar exported to grid~260 units/month
Net UnitsImport minus export (what you pay for)~10 net units
Energy ChargesNet units × tariff rate~Rs. 450
Fixed ChargesMeter rent + surcharges (NOT offset by solar)Rs. 1,500–3,500
Total BillEnergy + fixed + taxes~Rs. 3,000–6,000
Pre-solar billWithout solar (same consumption)~Rs. 24,000+
⚠️ Fixed charges (meter rent, Fuel Adjustment Charges, taxes) are NOT offset by solar generation. Your FESCO bill will never go to zero — minimum Rs. 1,500–3,500/month even with large solar system. This is normal for all DISCOs.

FESCO processes net metering applications at the Canal Road CSC. Ensure your installer has prior FESCO net metering approvals — some smaller installers are unfamiliar with FESCO's specific document requirements.

8. How Much You Save with FESCO Net Metering

FESCO area has 5.0 peak sun hours/day — good solar resource.

System SizeMonthly GenerationMonthly Bill ReductionAnnual SavingsPayback (On-Grid)
3 kW~318 kWhRs. 14,340–15,535~Rs. 172,200~2 yrs
5 kW~531 kWh/month~Rs. 23,900/month~Rs. 2.87 Lac/year~2 yrs
7 kW~743 kWhRs. 33,460–35,850~Rs. 401,800~2 yrs
10 kW~1062 kWhRs. 47,800–50,190~Rs. 574,000~1.9 yrs

After 15% system losses. Savings at Rs. 45/unit. Load-shedding areas: add Rs. 10,000–20,000/month hybrid generator savings.

Load-shedding bonus: For FESCO areas with 8–12 hrs daily load-shedding — a hybrid system with 10kWh Pylontech battery adds Rs. 10,000–20,000/month in eliminated generator costs, improving payback period to 2.5–3.5 years even on higher-cost hybrid systems.

9. FESCO-Specific Notes & Tips

FESCO's industrial connections often have higher sanctioned loads — commercial solar above 10kW is very viable. For residential buyers, the strong textile industry demand for installers means competitive pricing and good expertise in Faisalabad city. Outstation areas (Jhang, Mianwali) should verify local installer capability for net metering applications before committing.

Load-shedding by area:

Faisalabad city: 8–12 hrs. Sargodha: 8–12 hrs. Jhang/TTS: 10–14 hrs. Mianwali/Khushab: 12–16 hrs.

Best inverter recommendation for FESCO area:

For most FESCO residential buyers: GoodWe ES/EM hybrid inverter is the top recommendation — sub-20ms switching handles Pakistan's sudden load-shedding, generator input is critical for FESCO's outage hours, and SEMS monitoring lets you track generation from your phone. Solis RHI is the best budget alternative. Avoid on-grid inverters in any FESCO area with 6+ hours daily load-shedding.

Frequently Asked Questions

FESCO net metering typically takes 6–12 weeks: Faisalabad city 6–9 weeks. Sargodha 7–11 weeks. Outstation offices (Jhang, Mianwali) 10–14 weeks. Submit at the Canal Road CSC in Faisalabad for fastest processing. Ensure documents are complete — incomplete applications add 2–4 weeks.

Strongly yes. Faisalabad has 5.0 peak sun hours (same as Lahore), 8–14 hours daily load-shedding in most areas, and high electricity bills from heavy appliance use. A 5kW hybrid system with 10kWh battery saves Rs. 35,000–45,000/month (electricity + generator) with 2.5–3.5 year payback.

CNIC copy (account holder), latest FESCO bill, application form (FESCO CSC se milega), single-line diagram (installer banata hai), inverter NEPRA approval certificate, solar panel datasheets, AEDB installer certificate, installation completion certificate.

Yes — industrial and commercial connections in FESCO territory are eligible for net metering. Three-phase systems require 3-phase inverters and 3-phase bi-directional meters. Large systems (above 100kW) may require NEPRA licence separately. Contact FESCO's engineering department for large commercial applications.

GoodWe ES/EM hybrid is recommended for Faisalabad residential — widest local dealer presence, sub-20ms switching for 8–14 hour load-shedding, and generator input for extended outages. Solis RHI is a good budget alternative with strong Faisalabad availability. Avoid on-grid inverters in areas with 8+ hours daily outage.

Government fees: Application Rs. 3,000–5,000 + Bi-directional meter Rs. 3,500–7,000 + sealing Rs. 1,000–2,000 = total Rs. 7,500–14,000 directly to FESCO. Your installer's net metering handling fee: Rs. 10,000–20,000 (should be in contract). Timeline: 6–12 weeks depending on your area within FESCO territory.

Ready to Apply for FESCO Net Metering?

Connect with an AEDB-registered installer experienced with FESCO applications in your area.

☀️ Size Your System 📩 Find AEDB Installer