LESCO Net Metering 2026 — Complete Process, Fees, Documents & Timeline

🔌 LESCO Net Metering 2026 — Complete Process, Fees, Documents & Timeline

Everything you need to know about LESCO net metering in Lahore: step-by-step application, required documents checklist, exact fees in PKR, inspection timeline, billing explained, how much you'll save, and what to do if LESCO delays your application.

📅 Updated May 2026  |  ⚡ LESCO — Lahore  |  ⏱️ 8 min read

📋 Step-by-Step Process 📄 Documents Checklist 💰 Fees in PKR ⏱️ 4–8 Week Timeline

1. LESCO Net Metering — Overview

LESCO (Lahore Electric Supply Company) is the distribution company supplying electricity to Lahore, Sheikhupura, Nankana Sahib and surrounding districts. LESCO administers net metering in its territory under NEPRA's Net Metering Regulations 2015 (amended 2025).

4–8 wks
Approval timeline
1 MW
Maximum system size
25 yrs
Net metering license
Fastest
Pakistan DISCO ranking

LESCO is consistently the fastest and most organized DISCO for net metering in Pakistan. They have a dedicated solar processing team at the Gulberg CSC and have approved thousands of residential and commercial solar installations.

2. Who is Eligible for LESCO Net Metering?

  • LESCO connection: Your electricity must be supplied by LESCO (Lahore, Sheikhupura, Nankana Sahib)
  • System size: Solar system must not exceed your sanctioned load. Check your bill for sanctioned load (kW)
  • Consumer categories: Domestic (residential), commercial, and industrial connections all eligible
  • Inverter requirement: Must use a NEPRA-approved inverter — all major brands are approved (verify your exact model)
  • AEDB installer: System must be installed by an AEDB-registered installer
  • Maximum size: Up to 1,000kW (1MW) — residential systems well within this
⚠️ Sanctioned load check: If your sanctioned load is 5kW and you want to install a 7kW solar system, you must first apply to increase your sanctioned load (separate LESCO application and fee). Most DHA/Gulberg connections have 5–10kW sanctioned load. Check your electricity bill — it shows sanctioned load in kW.

3. Complete LESCO Net Metering Application Process

1

Solar System Installation

Your AEDB-registered installer installs the complete solar system. Inverter must be NEPRA-approved. All wiring, earthing, and protection devices must meet LESCO's technical standards. Do not attempt net metering application before installation is complete.

Before application
2

Prepare All Documents

Gather personal documents (you provide) and technical documents (your installer prepares). See complete checklist in Section 4. Incomplete applications are a major cause of delays — get everything right first time.

Before submission
3

Application Submission at LESCO CSC

Your installer submits the application at the nearest LESCO Customer Service Centre with complete documentation. Pay the application processing fee. Get the application reference number and submission date in writing. LESCO's Gulberg CSC is recommended for fastest processing.

Day 1
4

LESCO Technical Inspection

LESCO's technical team visits your premises. Be present or ensure your installer is present. They inspect: inverter installation and settings, DC and AC wiring, earthing/grounding, surge protection, and disconnection switches. They verify the system matches the submitted single-line diagram. Inspection takes 30–60 minutes.

2–4 weeks after submission
5

Application Approval

If inspection passes, LESCO issues approval letter. Your installer coordinates with LESCO for meter installation scheduling. If inspection fails (common reasons: missing surge protector, incorrect earthing, non-approved inverter model), rectify the issues and request re-inspection.

1–2 weeks after inspection
6

Bi-Directional Meter Installation

LESCO replaces your existing meter with a bi-directional (import/export) smart meter. This meter records both units imported from the grid and units exported from your solar system. Meter installation is done by LESCO team — your presence is required.

1–2 weeks after approval
7

Net Metering Active — Credits Begin

From the next billing cycle after meter installation, your LESCO bill shows import and export units. Net metering credits appear as reductions in your monthly bill. Your 25-year net metering license is issued.

Next billing cycle

4. Required Documents — Complete Checklist

📋 You Provide (Personal Documents)

  • CNIC copy (electricity account holder)
  • Latest LESCO electricity bill (shows reference number, sanctioned load, address)
  • Property ownership proof or tenancy agreement
  • Completed application form (obtained from LESCO CSC or your installer)
  • Passport-size photograph of account holder

🔧 Installer Prepares (Technical Documents)

  • Single-line electrical diagram of solar installation
  • Inverter datasheet with NEPRA approval certificate
  • Solar panel technical datasheets
  • Installation completion certificate (signed by AEDB installer)
  • AEDB installer registration certificate (current)
  • System summary (capacity, panel count, inverter model)
Pro tip: Make 3 sets of all documents before submission — one for LESCO, one for your records, one for your installer. Photograph every document front and back. LESCO offices occasionally misplace documents — having copies prevents delays of weeks. Keep the submission receipt with the date stamped.

5. LESCO Net Metering Fees in PKR

Fee ItemAmount (PKR)Paid ToWhen
Application Processing FeeRs. 3,000–5,000LESCO (at CSC)At application submission
Bi-Directional Meter CostRs. 3,500–7,000LESCOAt meter installation
Meter Sealing FeeRs. 1,000–2,000LESCOAt meter installation
Net Metering Application (Installer)Rs. 10,000–20,000Your installerPart of installation contract
Total Government FeesRs. 7,500–14,000LESCO directlySplit across process

Total LESCO fees are Rs. 7,500–14,000 paid directly to LESCO. Your installer's net metering handling fee (Rs. 10,000–20,000) should be included in your installation contract. Confirm this is included before signing — some budget installers exclude it.

6. LESCO Customer Service Centre Locations (Net Metering)

  • Gulberg CSC (Recommended — fastest): 7-A, Gulberg III, Lahore. Dedicated solar team. Most experienced with net metering applications.
  • DHA CSC: Phase V, DHA, Lahore. Good for DHA area residents.
  • Mall Road CSC (Head Office): LESCO Head Office, Mall Road. Handles escalations and complex cases.
  • Johar Town CSC: Main Boulevard, Johar Town. Covers Johar Town, Township, Model Town areas.
  • Cantt CSC: Covers Cantt and adjacent areas.
⚠️ Always visit the CSC covering your connection's area — not just the nearest CSC. Check your electricity bill header for the division code. Applications submitted to the wrong CSC are redirected and cause delays.

7. LESCO Net Metering Billing Explained

After your bi-directional meter is installed, your monthly LESCO bill changes significantly:

Bill Line ItemWhat It MeansExample (5kW, 500 units consumed)
Units ImportedElectricity you drew from LESCO grid280 units (night + daytime shortfall)
Units ExportedExcess solar sent to LESCO grid250 units (daytime excess)
Net Units BilledImport minus export30 net units
Energy Charges30 units × current LESCO tariff~Rs. 1,350 (at Rs. 45/unit avg)
Fixed ChargesMeter rent + FC surcharge (NOT offset by solar)Rs. 1,500–3,000/month
Total BillEnergy charges + fixed charges + taxes~Rs. 4,000–6,000
Pre-solar bill (same consumption)500 units × Rs. 45 + fixed charges~Rs. 26,000+
⚠️ Fixed charges cannot be eliminated: LESCO's meter rent, Fuel Adjustment Charges (FAC), and other fixed surcharges are applied regardless of how much solar you generate. Even if you export more than you import, you'll still pay Rs. 1,500–3,000/month minimum. This is why your LESCO bill never goes to zero with solar.

8. How Much You Save with LESCO Net Metering

System SizeMonthly Generation (Lahore)Monthly Bill ReductionAnnual SavingsPayback Period
3 kW on-grid~320 kWh avgRs. 12,000–15,000~Rs. 1.6 Lac~2 yrs
5 kW on-grid~530 kWh avgRs. 20,000–24,000~Rs. 2.6 Lac~2 yrs
7 kW on-grid~745 kWh avgRs. 28,000–33,000~Rs. 3.7 Lac~2 yrs
10 kW on-grid~1,065 kWh avgRs. 40,000–47,000~Rs. 5.2 Lac~1.9 yrs

Savings include both self-consumption (avoided import at retail rate) and net metering credits for exported units. Lahore smog-adjusted annual generation. Rs. 45/unit average tariff.

9. LESCO Delays & How to Escalate

NEPRA mandates DISCOs process net metering applications within 30 days of complete documentation. If LESCO exceeds this:

  • Call LESCO Helpline: 042-111-000-118 — reference your application number and request status update
  • Visit CSC in person: Request to speak with the solar/net metering supervisor. Bring copies of all submitted documents and your submission receipt.
  • File NEPRA complaint: NEPRA's consumer complaint portal (nepra.org.pk) — provide application reference, submission date, and DISCO name. NEPRA typically responds within 15 working days and follows up with LESCO.
  • Common delay causes: Incomplete documentation (most common), inspector availability, meter procurement delays, clerical backlog. Each has a different solution — confirm with LESCO why specifically your application is delayed.

Frequently Asked Questions

LESCO typically processes net metering in 4–8 weeks from complete application: Submission to inspection: 2–4 weeks. Inspection to approval: 1–2 weeks. Approval to meter installation: 1–2 weeks. Total: 4–8 weeks. LESCO is Pakistan's fastest DISCO. Gulberg CSC is fastest within LESCO. Ensure complete documentation first time to avoid delay cycles — an incomplete application adds 2–4 weeks minimum for re-submission.

  • CNIC copy (account holder)
  • Latest LESCO electricity bill
  • Application form
  • Single-line electrical diagram (installer prepares)
  • Inverter NEPRA approval certificate
  • Solar panel datasheets
  • AEDB installer certificate
  • Installation completion certificate

Your AEDB-registered installer prepares all technical documents. You provide the personal and connection documents.

  • Application processing fee: Rs. 3,000–5,000 (paid at LESCO CSC)
  • Bi-directional meter cost: Rs. 3,500–7,000 (paid at meter installation)
  • Meter sealing fee: Rs. 1,000–2,000
  • Total LESCO fees: Rs. 7,500–14,000
  • Installer net metering handling fee: Rs. 10,000–20,000 (part of installation contract)

No — LESCO requires all net metering applications to be submitted by an AEDB-registered installer. The application requires technical documents (single-line diagram, installation certificate, AEDB certificate) that only registered installers can provide. DIY solar installation also cannot be approved for net metering — LESCO requires AEDB installer certification. The installer's fee (Rs. 10,000–20,000) is a small cost relative to the system investment and covers both installation quality and net metering application handling.

LESCO net metering credits roll forward month-to-month — if you export more than you import in a month, the credit reduces your next month's bill. At the annual settlement (typically at financial year end), unused credits may lapse or be paid out at the "avoided cost" rate — which is lower than the retail tariff. Practically: size your system so annual generation approximately matches annual consumption. Don't massively oversize — credits beyond annual consumption provide diminishing returns in Pakistan's current LESCO net metering framework.

  • Inverter model vs submitted documents — must match exactly. Wrong model = instant rejection.
  • AC wiring from inverter to distribution board — must be correct gauge and properly protected
  • DC cabling — must have appropriate DC fuse/MCB and surge protection device (SPD)
  • Earthing/grounding — inverter frame and panel frames must be properly earthed
  • AC disconnection switch — must be accessible for LESCO linemen safety
  • Physical installation quality — no exposed conductors, proper weatherproofing on outdoor components

Most common rejection reasons: missing surge protection device (SPD), inadequate earthing, inverter not matching submitted documents.