FESCO Net Metering — Process, Fees & Timeline in Pakistan

FESCO Net Metering — Process, Fees & Timeline

Complete guide to FESCO net metering for residential and commercial solar installations in Pakistan. Learn about the step-by-step process, fees, expected timelines, and required documents for smooth approval.

Start Process

What is FESCO Net Metering?

FESCO net metering allows solar system owners to export surplus electricity to the grid and receive credit on their electricity bills. This system helps reduce overall energy costs while promoting renewable energy adoption in Pakistan.

Step-by-Step Process

1. Application Submission

Submit your net metering application through FESCO's online portal or local office with all required details and documents.

2. Site Inspection

FESCO team inspects your solar installation site to verify system specifications and compliance with safety standards.

3. Fee Payment

Pay applicable net metering fees, including meter installation charges, processing fees, and any connection fees.

4. Meter Installation & Approval

FESCO installs a bi-directional net meter and approves your connection to the grid.

Net Metering Fees

Fee TypeEstimated Cost (PKR)
Application Fee500 – 1,000
Meter Installation5,000 – 15,000
Processing / Inspection Fee2,000 – 5,000
Total Estimated Cost7,500 – 21,000

Expected Timeline

  • Application Submission: 1-2 days
  • Site Inspection: 3-5 days
  • Fee Processing: 1-2 days
  • Meter Installation & Final Approval: 7-10 days
  • Total Estimated Time: 2-3 weeks

Required Local Documents

  • Copy of CNIC / National ID
  • Proof of property ownership or tenancy agreement
  • Solar system design and capacity details
  • Electrical single-line diagram
  • Bank account details for bill crediting
  • Application form signed and submitted to FESCO